|

West Liberty Avenue at the intersection
with Brookline Boulevard (left) and Wenzel Avenue (right) in June 1916.
The roadway proceeds south to the city line and border with Dormont, located
at Pioneer Avenue
West Liberty Avenue, which runs
along Plummers Run Creek, was first laid out in 1839. The roadway
extended from Saw Mill Run and the Bell House Tavern southward to
the intersection with Potomac Avenue in Dormont. Rail lines were
installed in the early 1900s to service the growing communities of
West Liberty Borough, which would soon be annexed into the City of
Pittsburgh. The city line, located at the southern terminus of Pioneer
Avenue, was established in 1908 with the annexation of Beechview and
Brookline.
As the southern population boomed,
West Liberty Avenue was soon in need of infrastructure improvements,
including modernization of the road surface and trolley line. The
renovation process, which began in 1910, was an ongoing project which reached its
zenith in 1915. There were many challenges involved. Several residential homes
and businesses were located along the construction route. Some had to be
moved out of the construction path. Trolley service, which was the main
mode of transportation for most people, could not be disrupted. Construction
materials were transported by rail to a staging area at Pioneer Avenue and
hauled by wagon to the construction zones.
Storm and sewer lines were trenched
and run along the entire roadway. Plummers Run Creek was channeled into
underground culverts. Utility poles were relocated and new lighting
installed. The roadway was widened to four lanes and completely paved in
belgian block. The entire stretch of the rail line was reconstructed.
Sidewalks and other amenities completed the transformation. The reconstruction
was completed in December 1915. It was a major civic and transportation
improvement, much of which remained in use without change for nearly
seventy years. The blocks and trolley tracks are still there today,
forming the base of the current asphalt roadway.
The sequence of photos below shows
the 1915 construction project as it proceeded in stages. When completed,
the roadway's appearance had dramatically changed. West Liberty Avenue
was now a major artery connecting the City of Pittsburgh with the South
Hills and beyond. It was ready for the advent of motorized transportation.
This project was vital for the continued growth of the southern
communities.
March 1915 April 1915 May 1915 July 1915 August 1915 October 1915 December 1915 June 1916
<Compare with West Liberty Avenue in 1912>
Click on
images for larger pictures
March 1915

West Liberty Avenue at the intersection
with Brookline Boulevard and Wenzel Avenue in March 1915.
The narrow dirt roadway was paved only along the trolley line, which
doubled as a pedestrian walkway.
The West Liberty reconstruction project
began with the installation of modern storm and sewer lines. A trench was dug
from the city line north to Warrington Avenue. Crews followed to construct the
brick and concrete base. Many property owners ceded much of their front yards
for the upgrades. Some had to be moved. One home that needed moved stood at
the corner of West Liberty and Warrington Avenues.

From the City Line at the border with Dormont (left)
and near Stapleton Avenue (right) looking north.

Approaching the intersection with Brookline Boulevard
(left) and from Saranac Avenue (right) looking north.

At Belle Isle Avenue (left) and approaching
Pauline Avenue (right) looking north.

At Ray Avenue looking north towards the bend
that leads to Curran Hill and Capital Avenues.

Beyond Ray Avenue looking north (left) and
approaching the intersection of Curran Hill and Capital Avenues (right).

Approaching Stetson Street (left) looking north
and between Stetson and Cape May Avenue (right) looking south.

Approaching Cape May Avenue (left) and
Brookside Avenue (right) looking north.

Looking south towards Brookside Avenue (left) and
looking south from near the Pioneer Avenue intersection.

Looking north at Pioneer Avenue (left) and
looking south from the corner of West Liberty and Warrington Avenues.

The front and rear of the home at West Liberty and
Warrington that stood in the construction path.
April 1915

The intersection of Brookline
West Liberty Avenue and Saranac Avenue in April 1915 looking north.
The photos below show the trenching of the
sewer line that ran the length of West Liberty Avenue. The home at the corner of
Warrington Avenue that blocked the construction path was eventually lifted and
moved out of the way.

Sewer line work near Saranac Avenue (left),
and at Brookside Avenue, both looking south.

Sewer line north of Brookside Avenue. The
work went quickly.

Sewer line work near Brookside Avenue, looking
south (left) and north.

Sewer line work north of the intersection with
Pioneer Avenue, approaching Warrington Avenue. The home that stands in line
with the trench caused a delay until arrangements were made to lift and move the
home out of the construction path.

Left - The home was moved to a secure place.
Right - View from near Pioneer Avenue looking south.

Once the home was moved construction proceeded to
the corner of West Liberty and Warrington Avenues.
May 1915

The intersection of Brookline
Boulevard, West Liberty Avenue and Wenzel Avenue in May 1915. This photo
was taken
from the grounds of the Kerr estate, which ran along
the lower left side Wenzel Avenue for many years.
The photos below show the installation
of 10' by 6' sewer line at the northern end of West Liberty Avenue, near the
intersection with Pioneer, Saw Mill Run and Warrington Avenues.

Sewer line work near the intersection with
Pioneer Avenue.

Sewer line near Pioneer Avenue (left) and
the 10' by 6' line near the northern end of West Liberty Avenue.

The intersection of West Liberty and
Warrington Avenues, showing the home that was moved away from the sewer
path.
July 1915

West Liberty Avenue at the intersection
with Brookline Boulevard and Wenzel Avenue in July 1915.
Sewer line work is complete, the new trolley lines are in place
and road paving has begun.
By July of 1915, sewer lines
had been laid on the southern end of West Liberty Avenue. New trolley
lines were in place. The expanded roadway was being leveled
and prepared for paving.

Trenching for the new sewer line near Stetson
Street.

A Marion Steam Shovel and the resulting
sewer trench north of Cape May Avenue.

Sewer construction north of Cape May Avenue (left) and
the project staging area at Pioneer Avenue.
Materials were brought by rail, unloaded and transported were needed.

A new railroad abutment was constructed at
Pioneer Avenue so to support the
widening of West Liberty Avenue. The existing abutment blocked the path.

View from near Pioneer Avenue (left) looking
north and from Warrington Avenue (right) looking south.

Sewer and storm runoff emptied into Saw Mill
Run Creek and flowed west to the Ohio River.
August 1915

West Liberty Avenue at the intersection
with Brookline Boulevard and Wenzel Avenue in August 1915
showing the progress of the construction project on this southern section
of the roadway.
By August 1915, the southern portion
of the West Liberty Avenue expansion was nearing completion. The project
was not as far along near Capital Avenue and sections further north. Much
work remained to be completed. The sewer lines gradually increased in size
and scope in the northern portions of the roadway.

From the City Line at the border with Dormont (left)
and near Stapleton Avenue (right) looking north.

Beyond Brookline Boulevard (left) and at Saranac
Avenue (right) looking north.

Approaching Belle Isle Avenue (left) and Pauline
Avenue (right) looking north.

Approaching Ray Avenue (left) and the intersection
with Curran Hill and Capital Avenues (right) looking north.

Sewer trench between Ray Avenue and Capital Avenue
looking north (left) and south (right).

View from Capital Avenue looking south showing
two 39Brookline trolley cars heading north towards downtown Pittsburgh.

Sewer line trench near Ray Avenue looking
south.

Approaching Curran Hill Avenue and Capital
Avenue looking north.

Sewer trench near Stetson Street looking
north.

The sewer trench near Cape May
Avenue, looking north.

Looking north from Brookside Avenue (left) and
looking south from Pioneer Avenue (right).

Looking towards the intersection with Pioneer
Avenue from the south (left) and north (right).
October 1915

West Liberty Avenue at the intersection
with Ray Avenue looking north towards the intersection with Capital
Avenue.
By October 1915 progress had been
made near Capital Avenue and sections further north. The upgraded trolley
tracks were being laid and the roadway prepared for paving.

Approaching Ray Avenue (right) and from
Stetson Street (right) looking north.

View from Cape May Avenue (left) and
Brookside Avenue (right) looking north.

Looking towards the intersection with Pioneer
Avenue from the south (left) and north (right).

Looking towards Pioneer Avenue from the
intersection of West Liberty and Warrington Avenues.
December 1915

West Liberty Avenue near the intersection
with Wenzel Avenue (left) and Brookline Boulevard (right) in December
1915.
By December 1915 the project was
at or near completion. After the belgian block roadway was completed, it
was covered in sand and dirt, which was then packed down by the constant
wagon traffic. Eventually it would either seep down between the bricks or
be washed away by the rain.

Approaching Saranac Avenue (left) and Belle
Isle Avenue (right) looking north.

Approaching Pauline Avenue (left) and Ray
Avenue (right) looking north.

Looking north from Ray Avenue towards the
intersection with Curran Hill and Capital Avenues.

Approaching Curran Hill and Capital Avenues (left)
and at Stetson Street (right) looking north.

At Cape May Avenue (left) and Brookside
Avenue (right) looking north.

Looking south from the Pioneer Avenue
intersection.

Looking north towards Pioneer Avenue (left) and
looking south from the corner of West Liberty and Warrington Avenues.
June 1916

West Liberty Avenue at the intersection
with Brookline Boulevard (left) and Wenzel Avenue (right) in June 1916.
The roadway proceeds south to the city line and border with Dormont, located
at Pioneer Avenue
By June of 1916 the West Liberty Avenue
reconstruction project was complete. The discomfort and disruption to the
homeowners, travellers and trolley service were over. Life could get back to
normal. This major improvement in both civic and transportation infrastructure
was a major influence in the growth and development of the southern neighborhoods
of the City of Pittsburgh and the suburban communities of the South Hills.

From the City Line (left) and from near
Stapleton Avenue (right) looking north.

From Brookline Boulevard (left) and at
Saranac Avenue (right) looking north.

Approaching Pauline Avenue looking
north.

Approaching Ray Avenue (left) and the
intersection with Ray Avenue (right) looking north.

Approaching Curran Hill and Capital Avenues (left)
and from Stetson Street (right) looking north.

Looking north from Cape May Avenue (left)
and Brookside Avenue (right).

Looking south from Pioneer Avenue (left)
and from the intersection of West Liberty and Warrington Avenues.
|